Question: could you please answer week 4 5 6 and 8 and projected on hand inventory for 2 and 8 Milford Manufactures is trying to develop
could you please answer week 4 5 6 and 8 and projected on hand inventory for 2 and 8
Milford Manufactures is trying to develop its master schedule for the next 8 weeks. Below, you will find the forecasted values for Weeks 1 through and the actual customer orders for Weeks 1 through 4. 4 1 150 125 2 150 130 Week Forecast Customer Orders 5 140 6 140 7 160 8 160 150 145 150 160 The on hand inventory for Week 15 30 units and the MPS lot site is 190 units What would be the available to promise quantity in Week 47
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock