Question: Course dashboard Question 4 Let's assume that the activity X has a slack time which equals 0. This means that (CLOP23) Not yet answord Marked
Course dashboard Question 4 Let's assume that the activity X has a slack time which equals 0. This means that (CLOP23) Not yet answord Marked out of 1.00 Select one: Flag question O a. Activity X is on the critical path and any delay of the activity X will lead to the delay of the whole project. O b. Activity X is on the critical path and its time cannot be crushed. O c. Activity X is on the near critical path and any delay of the activity X will lead to the delay of the whole project O d. Activity X is on the near critical path and its time cannot be crushed. NEXT PAGE VIOUS PAGE