Question: Course: Project Management Program : Master of Engineering Management Question: A project manager has collected the following information for her new software application project to
Course: Project Management
Program: Master of Engineering Management
Question:
A project manager has collected the following information for her new software application project to create a customer database.

Activity ID Activity Description Predecessor Duration (Day) Optimistic Most Likely Pessimistic A Systems design 6 8 10 B Subsystem A design A 2 3 C Subsystem B design A 1 3 5 D Subsystem C design A 40 60 80 E Program A B 30 40 50 F Program B C 1 2 3 G Program C D 1 2 3 H Subsystem A test E, F 15 20 25 = Subsystem B test G 5 10 15 C Subsystem C test H, I 5 10 15 K Integration J 6 12 18 L Integration test K 1 3 5