Question 5. Scenario Based:
Consider the following activity table:

a). Draw (1) Project Network (using ADM), (2) Compute and list critical path, and (3) list project duration.
b). Draw the Gantt chart for the above Project Network .
# Activity A Plan B Select the Team C Hardware selection D Requirements E Prototype F Logical design G Physical design H Install & Testing of hardware I Coding J User Manual K Testing L Installation M Training Duration Precedents (+ Represents lag (days) 1 1 3 B 3 A and B+2 2 B 3 D and E 4 F 2 6 B+2 and G 3 3 I 4 K and H 3 L