Question: Course subject is project management. 1. Payback Analysis Two new wind-farm tower projects are proposed for a small company that installs them in south western
Course subject is project management.
1.Payback Analysis Two new wind-farm tower projects are proposed for a small company that installs them in south western Pennsylvania. Project A will cost $250,000 to complete and is expected to have an annual net cash flow of $75,000. Project B will cost $150,000 to complete and should generate annual net cash flows of $52,000. As a small company, the owner and senior management team are very concerned about their cash flow. Use the payback period method and determine which project is better from a cash flow standpoint. Show your work and include any formulas used to calculate PP.