Question: CPM By using the Legend given below and information given in the Table, Legend: Early Start Total Float Early Finish Activity Name Late Start Duration

CPM

By using the Legend given below and information given in the Table,

Legend:

Early Start

Total Float

Early Finish

Activity Name

Late Start

Duration

Late Finish

Table:

Activity Name

Duration (days)

Dependence

B

10

-

E

15

B

X

20

B

Z

25

B

T

10

E, X

A

15

X, Z

C

15

E, X, Z

Y

20

A, K

D

30

T, C

K

35

B

  1. Construct the precedence Network diagram
  2. By using Activity on Node (AoN) methods, compute the total project duration.
  3. Identify the critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!