Question: CPM By using the Legend given below and information given in the Table, Legend: Early Start Total Float Early Finish Activity Name Late Start Duration
CPM
By using the Legend given below and information given in the Table,
Legend:
| Early Start | Total Float | Early Finish |
| Activity Name | ||
| Late Start | Duration | Late Finish |
Table:
| Activity Name | Duration (days) | Dependence |
| B | 10 | - |
| E | 15 | B |
| X | 20 | B |
| Z | 25 | B |
| T | 10 | E, X |
| A | 15 | X, Z |
| C | 15 | E, X, Z |
| Y | 20 | A, K |
| D | 30 | T, C |
| K | 35 | B |
- Construct the precedence Network diagram
- By using Activity on Node (AoN) methods, compute the total project duration.
- Identify the critical path.