Question: CPM Homework Assignment Construction of a building is based on the following CPM network: Activity Predecessor Successor Normal time Normal cost Crash time Crash cost

CPM Homework Assignment

Construction of a building is based on the following CPM network:

Activity

Predecessor

Successor

Normal time

Normal cost

Crash time

Crash cost

A

B, C, D

6

$100

2

$150

B

A

E, C

8

80

2

140

C

B, A

F

2

40

1

60

D

A

F, G

3

80

2

120

E

B

G

5

80

3

140

F

C, D

G

5

60

1

100

G

E, F, D

6

120

2

160

  1. Draw the network for this project.
  2. Do a forward pass and a backward pass.
  3. What is the critical path?
  4. What is the total normal project completion time?
  5. What is the total cost for normal project completion?
  6. How much will it cost to crash the project completion by one day (What is the new total normal cost for project completion)?
  7. Can the project completion be crashed by two days? Why or why not? If so, how?
  8. What will be the new total normal cost for project completion if it is crashed by two days?
  9. What is the minimum time for project completion?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!