Question: CPM Homework Assignment Construction of a building is based on the following CPM network: Activity Predecessor Successor Normal time Normal cost Crash time Crash cost
CPM Homework Assignment
Construction of a building is based on the following CPM network:
| Activity | Predecessor | Successor | Normal time | Normal cost | Crash time | Crash cost |
| A |
| B, C, D | 6 | $100 | 2 | $150 |
| B | A | E, C | 8 | 80 | 2 | 140 |
| C | B, A | F | 2 | 40 | 1 | 60 |
| D | A | F, G | 3 | 80 | 2 | 120 |
| E | B | G | 5 | 80 | 3 | 140 |
| F | C, D | G | 5 | 60 | 1 | 100 |
| G | E, F, D |
| 6 | 120 | 2 | 160 |
- Draw the network for this project.
- Do a forward pass and a backward pass.
- What is the critical path?
- What is the total normal project completion time?
- What is the total cost for normal project completion?
- How much will it cost to crash the project completion by one day (What is the new total normal cost for project completion)?
- Can the project completion be crashed by two days? Why or why not? If so, how?
- What will be the new total normal cost for project completion if it is crashed by two days?
- What is the minimum time for project completion?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock