Question: CPM PERT CHART Activity Predecessor activity Optimistic time (a) Likely time (m) Pessimistic time (b) Expected Time T =(a+4m+b)/6 A ---- 1 2 4 B

CPM PERT CHART

Activity

Predecessor activity

Optimistic time

(a)

Likely time

(m)

Pessimistic time

(b)

Expected Time

T =(a+4m+b)/6

A

----

1

2

4

B

----

3

3.5

4

C

----

10

12

13

D

----

4

5

7

E

----

2

4

5

F

A

6

7

8

G

B

2

4

5.5

H

C

5

7.7

9

I

C

9.9

10

12

J

C

2

4

5

K

D

2

4

6

L

E

2

4

6

M

F,G,H

5

6

6.5

N

J,K,L

1

1.1

2

O

I,M

5

7

8

P

N

5

7

9

  1. Calculate the expected project time
  2. Draw By HAND PERT Chart:
  3. Count the following:
  • Early Start (ES)
  • Early Finish (EF)
  • Lately Start (LS)
  • Lately Finish (LF)
  • Slack
  1. Calculating the redundant times of activities and determining the critical path.

Please drow the PERT chart by hand with the numbers and detailes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!