Question: CPM problem. Draw the network, find the time to complete, the critical path, and the slack for each activity for the following project: Activity Follows
CPM problem.
Draw the network, find the time to complete, the critical path, and the slack for each activity for the following project:
Activity Follows Time
A - 5
B - 6
C A 4
D A 4
E B, C 5
F E 3
G D, F 4
H E 5
I G, H 3
J I 4
K I 5
L J, K 4
M K 5