Question: CPM Problem G 8 4 B D 7 8 7 2 E H 9 4 5 C F Dur ES EF A LS LF All

CPM Problem G 8 4 B D 7 8 7 2 E H 9 4 5 C F DurCPM Problem G 8 4 B D 7 8 7 2 E H 9 4 5 C F Dur

CPM Problem G 8 4 B D 7 8 7 2 E H 9 4 5 C F Dur ES EF A LS LF All relationships are Finish to Start unless otherwise noted All durations are in Days 1. (24 points) The CPM network on the following page depicts the initial work of a team working on a consulting project. Answer the following questions: a. What is the duration of the project? b. Which activities are on the critical path? c. Which activity has the most float? d. What is the float of Activity D? e. What is the Float of Activity F? f. Which activities have the greatest schedule risk