Question: CPU Burst time Arrival time Process 7 0.0 P1 3 3.0 P2 1 7.0 P3 9 9.0 P4 2 12.0 P5 a) Draw a Gantt
| CPU Burst time | Arrival time | Process |
| 7 | 0.0 | P1 |
| 3 | 3.0 | P2 |
| 1 | 7.0 | P3 |
| 9 | 9.0 | P4 |
| 2 | 12.0 | P5 |
a) Draw a Gantt chart for illustrating the execution of these processes Using Short-Job- Time-First scheduling with preemption? b) Calculate the average Waiting time?
c) Calculate the Average Turnaround Time?