Question: CPU scheduling Process Arrival Time Burst Time Priority P1 0 8 8 P2 0 4 10 P3 4 1 6 P4 6 6 8 For
CPU scheduling
| Process | Arrival Time | Burst Time | Priority |
| P1 | 0 | 8 | 8 |
| P2 | 0 | 4 | 10 |
| P3 | 4 | 1 | 6 |
| P4 | 6 | 6 | 8 |
For Shortest Remaining Time draw the Gantt chart to illustrate how these processes would be scheduled, and calculate turnaround time per process and the wait time per process.