Question: CPU scheduling question: Consider the processes: (P1, 50, 25), (P2, 75, 30). The triples have the form (process, period, time). Assume that deadline and period
CPU scheduling question:
Consider the processes: (P1, 50, 25), (P2, 75, 30). The triples have the form (process, period, time). Assume that deadline and period are identical.
1:Can these two processes be scheduled using rate-monotonic scheduling? Explain.
2:Can these two processes be scheduled using earliest deadline-first (EDF) scheduling? Explain.