Question: Crane Company developed the following data: Beginning work in process inventory $ 120000 Direct materials used 520000 Actual overhead 540000 Overhead applied 510000 Cost of
Crane Company developed the following data:
| Beginning work in process inventory | $ 120000 |
| Direct materials used | 520000 |
| Actual overhead | 540000 |
| Overhead applied | 510000 |
| Cost of goods manufactured | 2020000 |
| Ending work in process | 90000 |
How much are total manufacturing costs for the period?
| $1990000 |
| $1050000 |
| $1930000 |
| $1570000 |