Crane Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking
Question:
Crane Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $970,000. The following data pertain to the construction period.
2020 | 2021 | 2022 | ||||
Costs to date | $292,500 | $487,500 | $660,000 | |||
Estimated costs to complete | 357,500 | 162,500 | 0 | |||
Progress billings to date (non-refundable) | 292,500 | 600,000 | 970,000 | |||
Cash collected to date | 262,500 | 550,000 | 970,000 |
(A)
Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
2020 | 2021 | 2022 | ||||
Gross profit / (loss) | $ | $ | $ |
(B)
Using the completed-contract method, calculate the estimated gross profit that would be recognized during each year of the construction period. (Do not leave any answer field blank. Enter 0 for amounts. Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
2020 | 2021 | 2022 | ||||
Gross profit / (loss) | $ | $ | $ |