Question: Crash Cost (5) Normal Cost (5) Activity Normal Time (weeks) Crash Time (weeks) 3 13000 5 7000 7 18000 12000 10 B 5000 7 7000

Crash Cost (5) Normal Cost (5) Activity Normal
Crash Cost (5) Normal Cost (5) Activity Normal
Crash Cost (5) Normal Cost (5) Activity Normal Time (weeks) Crash Time (weeks) 3 13000 5 7000 7 18000 12000 10 B 5000 7 7000 8 5000 D 6 5 4000 E 7 3000 6000 6 3 6000 7000 F G 7000 9000 4 3 a. What is the project completion time? (3 pts) b. What is the total cost of completing the project in normal time? (2 pts) c. If you wished to reduce the time required for completion of the project by 3 weeks which activities should be crashed and how much will the cost increase. (5 pts) m