Question: Crash Time (weeks) Immediate Predecessors none Maximum Weeks Reduced Activity N- Normal Normal Time Cost (weeks) ($) 3,000 5,000 2,000 3,000 4,000 4,000 2,000 Crash

Crash Time (weeks) Immediate Predecessors none
Crash Time (weeks) Immediate Predecessors none Maximum Weeks Reduced Activity N- Normal Normal Time Cost (weeks) ($) 3,000 5,000 2,000 3,000 4,000 4,000 2,000 Crash Cost _($) 18,000 11,000 10,000 12,000 12,000 6,000 10,000 10 OOO -NW- EF Q6: Project management How much money would it cost to reduce 7 weeks from the project duration if it was done in the cheapest way possible? Answer in thousands of dollars, so if your answer is $11,000, enter 11