Question: Crashing a schedule is reducing a project completion time by rearranging all tasks throwing less resources to the critical path renegotiating with management throwing additional

Crashing a schedule is reducing a project completion time by rearranging all tasks throwing less resources to the critical path renegotiating with management throwing additional resources to the critical path realign tasks in parallel