Question: CRASHING ASSIGNMENT B Legend Activity Code 8 E 3 Duration A C G > 5 2 9 F 4 D 6 Activity Normal Time Normal

CRASHING ASSIGNMENT B Legend Activity Code 8 E 3

CRASHING ASSIGNMENT B Legend Activity Code 8 E 3 Duration A C G > 5 2 9 F 4 D 6 Activity Normal Time Normal Cost Crash Time Crash Cost A 5 $300 5 $300 B C 8 2 250 100 400 100 Oymo 6 3 4 9 300 150 275 700 o cono na 600 300 300 900 Given the above network diagram: 1) perform the activities crashing until it can no longer be crashed. What is the total cost? 2) If there is a bonus of $125 per day for finishing early, what activities would be crashed, and how fast would the project be completed