Question: Create a critical path analysis based on the following information provided in the table and answer the questions identified below. Task Expected Time in Weeks
Create a critical path analysis based on the following information provided in the table and answer the questions identified below.
| Task | Expected Time in Weeks | Predecessor(s) |
| A | 6 | - |
| B | 7 | - |
| C | 10 | A |
| D | 5 | A, B |
| E | 8 | D |
| F | 4 | C, E |
| G | 3 | E |
1. What is the critical path for this project?
2. What is the total duration for the project?
3. What is the slack on each task (A, B, C, D, E, F, G)?
4. What task has the most slack?
5. What is the Earliest Start for Task E?
6. What is the Latest Start for Task B?
7. Do any tasks have the same Latest Finish? If yes, then identify the tasks.
8. Which task has the longest Earliest Finish?
9. What task has the longest duration?
10. What is your recommendation for the project if tasks that are NOT part of the critical path began to slip?