Question: Create a critical path analysis based on the following information provided in the table and answer the questions identified below. Task Expected Time in Weeks

Create a critical path analysis based on the following information provided in the table and answer the questions identified below.

Task Expected Time in Weeks Predecessor(s)
A 6 -
B 7 -
C 10 A
D 5 A, B
E 8 D
F 4 C, E
G 3 E

1. What is the critical path for this project?

2. What is the total duration for the project?

3. What is the slack on each task (A, B, C, D, E, F, G)?

4. What task has the most slack?

5. What is the Earliest Start for Task E?

6. What is the Latest Start for Task B?

7. Do any tasks have the same Latest Finish? If yes, then identify the tasks.

8. Which task has the longest Earliest Finish?

9. What task has the longest duration?

10. What is your recommendation for the project if tasks that are NOT part of the critical path began to slip?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!