Question: Create a Gantt Chart for the following software conversion project: Initiating Develop business case (5 days) Develop project charter (5 days) Meet with stakeholders ---identify
Create a Gantt Chart for the following software conversion project:
Initiating
Develop business case (5 days)
Develop project charter (5 days)
Meet with stakeholders
---identify stakeholders (1 day)
---inform stakeholders (2 days)
---organize and conduct a meeting (2 days)
Sign off (milestone)
Planning
Create project team (5 days)
Create communication plan (3 days)
Create scope statement (5 days)
Create WBS (3 days)
Create risk management plan (3 days)
Planning concluded (milestone)
Executing
Create contracts for software conversion
----identify suppliers (1)
----contact suppliers (2)
--- select supplier (3)
----create final contract (4)
Sign contract (milestone)
Install new software on servers (5 days)
Install new hardware on client machines (5 days)
Install new software on client machines (5 days)
Test new system (10 days)
Train users (10 days)
New software live (milestone)
Closing
Create report (5 days)
Project completed (milestone)