Question: Create a linear schedule for the following 1 2 , 0 0 0 foot - long Light Rail project, with 6 platforms, and indicate the

Create a linear schedule for the following 12,000 foot-long Light Rail project, with 6
platforms, and indicate the total project duration. (5 points)
Sequence of tasks:
Utility work, done in 4 segments (or "blocks") of 3,000 feet each, using 2 separate
work crews. 2 months duration per segment
Roadway work, done in 6 segments of 2,000 feet each, using only 1 crew. 1 month per
segment
Platforms, 6 total located at stations 00+00,20+50,50+00,70+20,90+00, and
120+00.1-month duration per platform
Signals, done in 6 segments of 2,000 feet each. 1 month per segment
Streetlights, 1,500 feet per month. Must be done linearly from 00+00 to 120+00
Overhead Contact Systems (OCS),2,500 feet per month. It must be done linearly from
00+00 to 120+00. It must keep a 12 month buffer with Streetlights.
Create a linear schedule for the following 1 2 ,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!