Question: Create a MS Project using the given data and explain the step by step procedure Today is August 4, 2020, and you have just been
Create a MS Project using the given data and explain the step by step procedure
Today is August 4, 2020, and you have just been hired by Conestoga College, a career school, to teach Word, Excel, and PowerPoint 2019 classes, which begin September 7, 2020. You have been given your schedule for the new term beginning in 5 weeks and have been asked to prepare all the course materials for your classes. In this project, you will create a task list of everything that you have been told needs to be done before the first day of class. In addition to that, you are to budget your time to also prepare yourself to teach Microsoft Word, Excel, and PowerPoint 2019. Study Guides have already been prepared but you must provide copies for each of the students on the roster you have been given. You will be working 3 days a week (MWF) for the next 5 weeks to prepare.
a. Open a Blank Project. Save the file as MGMT8490_Task5_YourLast_First_Name.
b. Set the Current date to 8/4/20 and Schedule from Project Finish Date of 9/8/20.
c. Create a new custom calendar called "Teaching Project". Verify that Working Time is on Work Weeks. Set Tuesday and Thursday as nonworking days. You will only be working on Monday, Wednesday, and Friday each week. Set the working time to 8:00 AM to 12:00 PM. Create an Exception named My Birthday, for August 26, 2020.
d. Assign "Teaching Calendar" to your MGMT8490_Task5_YourLast_First_Name project file.
e. Set the project to Auto Scheduled. f. Add the tasks provided in the table below:
1 Get new schedule 5 min
2 Review student list 1 hr
3 Verify subject criteria 1 hr
4 Make necessary corrections to student list 1 hr
5 Create labels with student name and course name 1 hr
6 Copy/print course materials 3 hrs
7 Select color-coded folders 1 hr
8 Add labels to folders 1 hr
9 Add course materials to folders 2 hrs
10 Get books from bookstore 2 hrs
11 Verify books and course material folders for each student 2 hrs
12 Verify attendance sheets with books and course materials 2 hrs
13 Read Word textbook and work through projects 2 days
14 Read Excel textbook and work through projects 2 days
15 Read PowerPoint textbook and work through projects 2 days
g. Delete Task 3. Rename Task 2 Verify students and courses
h. Delete Task 7. Rename the new Task 7 Add labels and course materials to folders
i. Add a new task between Tasks 10 and 11 with a duration of 0 days. Call it First Day
j. Set the 'First Day' as a milestone.
k. Change the duration of Create labels with student name and course name (Task 4) to 2 hrs.
l. Move Tasks 12 through 14 below Task 1.
m. Link Tasks 2-4 so they have a Finish-to-Start relationship.
n. Add your first and last name as a header on the right tab of the Gantt Chart. o. Save your file. Close the project file and submit the file to Task 5 Assignment folder.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts