Question: Create a Network Diagram for this foundation plan. Excavation 5 days Form Footing 4 days Reinforce Footing 2 days Place Footing Concrete 1 day Build
Create a Network Diagram for this foundation plan.
Excavation 5 days Form Footing 4 days Reinforce Footing 2 days Place Footing Concrete 1 day Build Wall Forms 6 days Erect Wall Forms 4 days Set Wall Reinforcing 6 days Place Wall Concrete 1 day Strip Footing Forms 2 days Strip Wall Forms 2 days Backfill 5 days