Question: Create a networking diagram with activity - on - arrow ( AOA ) method and critical path for the following task with a networking diagram

Create a networking diagram with activity-on-arrow (AOA) method and critical path for the following task with a networking diagram use predecessor and successor, slack and project completion time and all the tasks have dependency of finish to start except task 22,23,25
1- Initiation Phase (7 days) Task 1: Define Project Objectives, Scopes and Goals(2 days) Task 2: Identify Stakeholders(2 days) Task 3: Conduct Preliminarily Feasibility and Risk assessment(1 days) Task 4: Develop a High-Level Project Charter(2 days)2- Planning Phase (11 days) Task 5: Develop a detailed project plan(2 days) Task 6: Allocate Resources(2 days) Task 7: Define project budget and procurement needs(2 days) Task 8: Identify Risk Mitigation Strategies(2 days) Task 9: Create a communication plan for stakeholders(3 days)3- Execution Phase (36 days) Task 10: Create and refine wireframes & prototypes(4 days) Task 11: Implement Front End Components(7 days) Task 12: Develop Database and API's(7 days) Task 13: Develop User Authentication and User management(6 days) Task 14 : Integration With Front-end(5 days) Task 15 : Unit Testing, Debugging and Iteration(7 days)4- Monitoring and Controlling Phase (Duration : 7 Days): Task 16 : Track project process (2 days) Task 17 : Conduct weekly project reviews and status meeting(2 days) Task 18 : Address any scope creep and deviations(1 days) Task 19 : Test User Experience and Systems Functionality(1 days) Task 20 : Document Testing outcomes and Bug fixes(1 days)5- Closing Phase (Duration : 2.5 Days): Task 21 : Deploy The Project on the live server(0.5 days) Task 22 : Conduct Stakeholders reviews and Gather Feedback(0.5 days)(Task dependency is finish to start from task 21) Task 23 : Finalize documentation and User Manual(0.5 days)(Task dependency is Start to start from task 22) Task 24 : Conduct Post-Project Evaluations(0.5 days)(Task dependency is Start to start from task 23) Task 25 : Official Project handover and closure(0.5 days)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!