Question: Create a precedence activity network using the following details. PERT is preferred. Identify the critical path. Activity Depends on Duration (days) A - 5 B
Create a precedence activity network using the following
details. PERT is preferred.
Identify the critical path.
Activity
Depends on
Duration (days)
A
-
5
B
A
7
C
B
6
D
A
5
E
D
10
F
B
15
G
B
8
H
G
8
I
C
4
J
G
4
K
E, F
5
L
I, H
3
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts