Question: Create a table with the critical path courses necessary for the timely completion of your degree. The courses are listed below. After the table is

Create a table with the critical path courses necessary for the timely completion of your degree. The courses are listed below.

After the table is created, draw the network.

MG100 (no pre-requisities), AC200 (no pre-requisities), AC201 (AC200 pre-req), MK200 (no pre-requisities), FI300 (AC200&201 pre-reqs), MK301 (MK200 pre-req), MK302 (MK200 pre-req), MK400 (MK200,301,302 pre-reqs), BU400 (AC200,AC201,FI300 pre-reqs)