Question: Create a Work Breakdown Sturture for the below mentioned Bridge Construction ( Bridge Replacement ) . Russells Bridge, which crosses the Moorabool River, is located

Create a Work Breakdown Sturture for the below mentioned Bridge Construction (Bridge Replacement).
Russells Bridge, which crosses the Moorabool River, is located at coordinates -38.013136,144.177102, just North of the town of Bannockburn which is in the Golden Plains Shire and is approximately 20km NW of the city of Geelong. Following an inspection triggered by a recent major flooding event, it was observed that the bridge was unsafe due to undermining of the foundations and subsequent failure of some parts of the structure. It was immediately closed to heavy vehicular traffic and is operating as a single lane bridge with timed traffic lights for light vehicles (less than 2t GVM) at slow speeds (20kph).
After consideration of various options and in consultation with VicRoads, the Golden Plains Shire has decided to erect an entirely new bridge to replace the original.
The new bridge should include the following features:
1. The standard should be consistent with VicRoads as an Arterial (non-urban) Road and classified as a C Road
2. A two-lane carriageway for safe passage of vehicles.
3. The road surface height should not be less than the existing bridge
4. The carriageway should be wide enough to incorporate bicycle lanes in each direction.
5. Consideration should be given to material selection on the basis of sustainable production, maintenance costs and full life cycle costs.
Boundary conditions are The new bridge should be located as close as possible to the east of the old bridge whilst leaving sufficient separation for the construction activities and traffic flow to carry on independently.
Your design and plan will be responsible for the road construction necessary to integrate the new bridge as simply as possible into the existing road alignment.
Approvals are to be taken is You are to assume that state and local government approvals for the project have been granted and all necessary regulatory obligations have been met. The local community including relevant indigenous and environmental groups have been consulted during the approvals process and have no objections.Create a Work Breakdown Sturture for the below mentioned Bridge Construction (Bridge Replacement).
Russells Bridge, which crosses the Moorabool River, is located at coordinates -38.013136,144.177102, just North of the town of Bannockburn which is in the Golden Plains Shire and is approximately 20km NW of the city of Geelong. Following an inspection triggered by a recent major flooding event, it was observed that the bridge was unsafe due to undermining of the foundations and subsequent failure of some parts of the structure. It was immediately closed to heavy vehicular traffic and is operating as a single lane bridge with timed traffic lights for light vehicles (less than 2t GVM) at slow speeds (20kph).
After consideration of various options and in consultation with VicRoads, the Golden Plains Shire has decided to erect an entirely new bridge to replace the original.
The new bridge should include the following features:
1. The standard should be consistent with VicRoads as an Arterial (non-urban) Road and classified as a C Road
2. A two-lane carriageway for safe passage of vehicles.
3. The road surface height should not be less than the existing bridge
4. The carriageway should be wide enough to incorporate bicycle lanes in each direction.
5. Consideration should be given to material selection on the basis of sustainable production, maintenance costs and full life cycle costs.
Boundary conditions are The new bridge should be located as close as possible to the east of the old bridge whilst leaving sufficient separation for the construction activities and traffic flow to carry on independently.
Your design and plan will be responsible for the road construction necessary to integrate the new bridge as simply as possible into the existing road alignment.
Approvals are to be taken is You are to assume that state and local government approvals for the project have been granted and all necessary regulatory obligations have been met. The local community including relevant indigenous and environmental groups have been consulted during the approvals process and have no objections.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!