Question: Create an activity network diagram and find the critical path. Activity Predecessor A B D E F G H I J None A B B
Create an activity network diagram and find the critical path.
Activity Predecessor A B D E F G H I J None A B B D C C E, G F H,I Duration (days) 4 2 4 3 1 5 2 3 3 4 4 3 Start Date 1-Jan 5-Jan 7-Jan 7-Jan 8-Jan 11-Jan 11-Jan 13-Jan 15-Jan 19-Jan Days Complete Days Incomplete 1 1 3 2 1 2 2 3 4 3 3 1 1 1 0 3 0 0 0 0
Step by Step Solution
There are 3 Steps involved in it
The critical path is the sequence of act... View full answer
Get step-by-step solutions from verified subject matter experts
