Question: Create an activity network diagram and find the critical path. Activity Predecessor A B D E F G H I J None A B B

Create an activity network diagram and find the critical path.
Activity Predecessor A B D E F G H I J None

Activity Predecessor A B D E F G H I J None A B B D C C E, G F H,I Duration (days) 4 2 4 3 1 5 2 3 3 4 4 3 Start Date 1-Jan 5-Jan 7-Jan 7-Jan 8-Jan 11-Jan 11-Jan 13-Jan 15-Jan 19-Jan Days Complete Days Incomplete 1 1 3 2 1 2 2 3 4 3 3 1 1 1 0 3 0 0 0 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The critical path is the sequence of act... View full answer