Question: create an AON diagram for this ref Description Duration ( Months ) Immediate Predecessor 1 Stadium - - 2 Clear site 3 . 5 -

create an AON diagram for this ref Description Duration (Months) Immediate Predecessor
1 Stadium --
2 Clear site 3.5-
3 Demolish adjacent building 1.52
4 Set-up construction site 1.53
5 Drive support piles 62
6 Pour lower concrete bowl 65
7 Pour main concourse 63,6
8 Install playing field 4.53,6
9 Construct upper steel bowl 63,6
10 Install seats 67,9
11 Build luxury boxes 4.57,9
12 Install scoreboard 1.57,9
13 Install stadium infrastructure 67,9
14 Construct steel canopy 4.510
15 Install lights 1.514
16 Build roof track support 4.56
17 Construct roof 1016
18 Install roof tracks 4.516
19 Install roof 4.517,18
20 Inspection 0.58,11,13,15,19
21 Closeout 04,12,20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!