Question: = Create the current state map of the process The class is given the following information: Pre manufacturing Order entry time = 1 day Raw

= Create the current state map of the process The class is given the following information: Pre manufacturing Order entry time = 1 day Raw material ordering = 1 hour Raw material delivery time = 2 days Incoming inspection time, = 0 hours Process steps Cutting Bending Braiding Coating Packing Cycle Time (sec) 2 10 10 5 2 Changeover Time (min) 5 10 5 120 5 # Operators 1 2 1 2. 2 Defect rate % 10 5 1 1 0 Available (shifts) 3 1 2 3 1 Uptime % 60 90 80 85 100