Question: CREDIT FOR OLD WORK ON THOSE UNITS ON WHICH NONE OF THE WORK AFFECTED BY THE CHANGE HAD BEEN PERFORMED Contractor's Estimate Air Force 40
CREDIT FOR OLD WORK ON THOSE UNITS ON WHICH NONE OF THE WORK
AFFECTED BY THE CHANGE HAD BEEN PERFORMED
Contractor's Estimate
Air Force
40 hrs
70 hrs
In attempting to determine what credit should be given for the old work on those units on
which it had not been performed, Mr. Foster ran into considerable difficulty. He reviewed a copy
of the contractor's original estimate but the cost of the work affected by the change had not been
separated from the overall estimate.
Relating the ratio of the changed work to the total number of hours in the original estimate,
Mr. Foster determined that a credit of 70 hours should be used.
To this the contractor replied that while Mr. Foster's estimate of 70 hours for the changed
work in the original estimate was reasonable, he had again failed to take into account the
improvement curve. The contractor contended that the 70 hours was the average for the entire
quantity of 175 required by the contract while the credit should be based on the average for the
last 60 units which would be considerably below the average for the entire 175 units.
11. Is the contractor's approach a reasonable one?
12.
Assuming the buyer accepts the contractor's contention, should he require that the
contractor furnish an improvement curve to substantiate his claim?
MANUFACTURING BURDEN
Contractor
Air Force
180%
110%
The contractor had used a manufacturing burden rate of 180% in the change proposal. Mr.
Foster agreed that the increased rate would probably prevail during the period of performance for
the changed work. He felt, however, that since the contractor has used a rate of 110% in his
original proposal, that this rate should be used in pricing the change to prevent the contractor
from repricing what otherwise might be a loss contract.
QUESTIONS:
13. Do you agree with this approach of the cost analyst?
7
14. Assume that the situation was reversed, viz; that the contractor had used a rate of
180% in his original proposal and his rate for the period of performance of the
change was 110%, would you approach the matter any differently?
5.
MATERIAL
Mr. Foster reviewed the estimated quantities and associated costs for both old and new
material. Since he found no major discrepancies, he accepted the material costs without further
question.
6.
GENERAL AND ADMINISTRATIVE EXPENSE
Contractor
Air Force
15%
6%
Mr. Foster used the same approach in computing G & A as he had for the manufacturing
burden. The contractor had used 6% in his original estimate and Mr. Foster thought that the same
rate should be used in pricing the change.
QUESTIONS:
15.
Do you agree with this approach?
16. If the situation was reversed, viz; the contractor had used a G&A rate of 15% in
his original proposal, and his anticipated G&A rate during the period of
performance of the changed work was 6%, would you approach the matter any
differently?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
