Question: Crenshaw Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0 $256,000 $256,000 1 114,400 88,600 2 104,200 99,600 3
| Crenshaw Enterprises has gathered projected cash flows for two projects. |
| Year | Project I | Project J |
| 0 | $256,000 | $256,000 |
| 1 | 114,400 | 88,600 |
| 2 | 104,200 | 99,600 |
| 3 | 88,200 | 101,600 |
| 4 | 77,200 | 108,600 |
| a. | At what interest rate would the company be indifferent between the two projects? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) |
| b. | Which project is better if the required return is above this interest rate? |