Question: .Critical Path A. Complete the forward and backwards pass in the following example: 6 5 0 L 0 2 4 6 Legend ES ID EF
.Critical Path A. Complete the forward and backwards pass in the following example: 6 5 0 L 0 2 4 6 Legend ES ID EF LS Dur L B. What, in order, are the tasks on the critical path: C. What is the longest duration of the project? D. Looking at the project from question #1 determine the critical path: roject Crashing 0 Comoute the per day costs for crashing each activity