Question: Critical Path Exercise - In class practice Learning Activity 10 C Question 1:1 6 A 8 B 5 E 3 H 6 D 8 G
Critical Path Exercise - In class practice Learning Activity 10 C Question 1:1 6 A 8 B 5 E 3 H 6 D 8 G 2 F 1. Determine each tasks':a. Early start and early finish datesb. Late start and finish dates2. Calculate the float for each task3. Identify the critical path and the total days for the path4. If activity E changes from 5 days to 10 days, what is the impact on the critical path and total duration of the project?

Critical Path Exercise In class practice Learning Activity Question 1: 1. Determine each tasks': 3. Early start and early finish dates b. Late start and nish dates 2. lCalculate the oat for each task 3. Identify the critical path and the total days for the path 4. If activity E changes from 5 days to 10 days, what is the impact on the critical path and total duration of the project? I_m_E- m_ B A C H lend]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
