Question: Critical Path for Wedding Plans 6. Critical Path for Wedding Plans. To help with preparations, a couple has devised a project network to describe the
Critical Path for Wedding Plans
6. Critical Path for Wedding Plans. To help with preparations, a couple has devised a project network to describe the activities that must be completed by their wedding date. In addition, they have estimated the time of each activity (in weeks). LO 2 a. Identify the critical path. b. How much time will be needed to complete this project? c. Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? e. What is the schedule for activity E