Question: Critical path is the _ _ _ _ _ time possible to complete all tasks required to finish the project. Question 9 options: 1 )

Critical path is the _____ time possible to complete all tasks required to finish the project.
Question 9 options:
1)
most complex
2)
first
3)
longest
4)
shortest