Question One

A project has these activities, precedence relationships, and activity durations:

Activity Immediate Predecessor Activities Activity Duration (weeks)

a - 7

b a 9

c a 6

d a 12

e b,c 11

f c 14

g d 16

h c,b 16

i h 12

j e,f,g 18

a) Construct a CPM network for the project

b) What is the critical path? What is its duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!