Question: Critical Path Method (CPM) Program Evaluation and Review Technique (PERT) Study carefully the example I am sending on your phones then attempt the questions for
Critical Path Method (CPM)
Program Evaluation and Review Technique (PERT)
Study carefully the example I am sending on your phones then attempt the questions for your assignment.
Question One
A project has these activities, precedence relationships, and activity durations:
Activity Immediate Predecessor Activities Activity Duration (weeks)
a - 7
b a 9
c a 6
d a 12
e b,c 11
f c 14
g d 16
h c,b 16
i h 12
j e,f,g 18
a) Construct a CPM network for the project
b) What is the critical path? What is its duration?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
