Question: Critical Path Methods The network below represents a project being analyzed by Critical Path Methods. Activity durations are indicated on the network. a. Identify the
The network below represents a project being analyzed by Critical Path Methods. Activity durations are indicated on the network. a. Identify the activities on the critical path. b. What is the duration of the critical path? c. Calculate the amount of slack time at activity B. d. If activity E were delayed by 3 time units, what would be the impact on the project duration
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
