Question: Critical path Question #4 (Total 14 marks) Show all your work a) Given the following activities, predecessors, and times, draw a critical path network diagram
Critical path

Question #4 (Total 14 marks) Show all your work a) Given the following activities, predecessors, and times, draw a critical path network diagram (5 marks) b) What is the critical path? (3 marks) c) How long will it take to complete the project? (2 marks) d) What is the slack time for activity C? (2 marks) e) What is the slack time for activity I? (2 marks) Activity Immediate Predecessor Time (days) A - 3 B - 2 C - 6 DB 5 EA 3 FA 5 G E & D 4 H C 2 I F & G 4
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
