Question: Critical Tasks (in no particular order): Issue Development (7 days) Requirements gathering for: Hardware (22 days), Software (19 days) and Network (20 days) Identifying System
Critical Tasks (in no particular order): Issue Development (7 days) Requirements gathering for: Hardware (22 days), Software (19 days) and Network (20 days) Identifying System Interfaces (10 days) Identifying Software Team Staffing Requirements (2 days) Determine & Purchase Hardware (15 days) Determine & Purchase Software (30 days) Determine & Purchase Network Equipment (30 days) Build Interfaces (60 days) Install & Test Hardware (30 days) Install & Test Software (14 days) Install & Test Network Equipment (30 days) Test System (5 days) Train Hospital Staff on system (5 days)
| Preliminary Project Plan | Target Date | Actual Date |
| Define | ||
| Measure | ||
| Analyze | ||
| Improve | ||
| Control |