Question: ctivity Normal Time ( days ) Crash Time ( days ) Normal Cost Total Cost with Crashing Immediate Predecessor ( s ) A 5 4
ctivity
Normal Timedays
Crash Timedays
Normal Cost
Total Cost with Crashing
Immediate Predecessors
A
$
$
long dash
B
$
$ $
long dash
C
$
$
long dash
D
$
$
A
E
$
$
C
Part
By how many days should each activity be crashed to reduce the project completion time by days? Fill in the table below.
Enter
your responses as whole
numbers.
Activity
Each Activity Should be Reduced BY
days
A
enter your response here
B
enter your response here
C
enter your response here
D
enter your response here
E
enter your response here