Question: Current Attempt in Progress A limitation of the high - low method is that because it is based on only two extreme points, the high
Current Attempt in Progress
A limitation of the highlow method is that
because it is based on only two extreme points, the high and low activity levels, the cost equation may not be truly representative of the cost relationship.
it is costly to use because it uses a statistical technique to estimate the cost components.
it can only be used if the levels of activity cover a wide range.
it is complex to calculate.