Question: Current Attempt in Progress AON network diagram: Activity A B D E F G H B Normal Time (weeks) 3 4 6 6 6 5

Current Attempt in Progress AON network diagram:

Current Attempt in Progress AON network diagram: Activity A B D E F G H B Normal Time (weeks) 3 4 6 6 6 5 7 3 O Normal Cost ($) 500 600 800 1,500 1,750 1,200 1,500 500 G Crash Time (weeks) 2 3 (b) Identify the activities on the critical path. Critical activities: 3 4 4 5 5 3 Using the information given, (a) Calculate the completion time for this project. Project completion time - H Crash Cost ($) 900 700 1,300 2,150 2,250 1.200 1.800 500 weeks. Maximum weeks Reduced 1 1 3 2 2 0 2 0 Crash Cost per Week ($) 400 100 166.67 325 250 0 150 0