Question: Current Attempt in Progress Blue Company is constructing a building Construction began on February 1 and was completed on December 31. Expenditures were $1.944,000 on

 Current Attempt in Progress Blue Company is constructing a building Construction

Current Attempt in Progress Blue Company is constructing a building Construction began on February 1 and was completed on December 31. Expenditures were $1.944,000 on March 1, $1,224,000 on June 1, and $3,072,650 on December 31. Compute Blue's weighted average accumulated expenditures for interest capitalization purposes. Weighted Average Accumulated Expenditures $