Question: Current Attempt in Progress During 2023, Cullumber Company started a construction job with a contract price of $1,248,000. The job was completed in 2025. The
Current Attempt in Progress
During 2023, Cullumber Company started a construction job with a contract price of $1,248,000. The job was completed in 2025. The following information is available. The contract is non-cancellable.
Costs incurred to date
Estimated costs to complete
Billings to date (non-refundable)
Collections to date
2023
$312,000
468,000
234,000
210,600
2024
$643,500
214,500
702,000
631,800
2025
$834,600
1,248,000
1,111,500
(a)
Your Answer
Correct Answer (Used)
Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
2023
2024
2025
Gross profit / (loss)
$
187.200
105,300
120,900
(b)
Prepare all necessary journal entries for 2024. (Use Materials, Cash, Payables for costs incurred to date.) (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter O for the amounts. List all debit entries before credit entries.)
Account Titles and Explanation
Debit
Credit
(To record cost of construction)
(To record progress billings)
(To record collections)
(To record revenues)
(To record construction expenses)