Question: Current Attempt in Progress During March. Patt, Inc. purchases and use 8.800 pounds of materials costing $95.640 to make 4,000 tiles Patt's standard material cost
Current Attempt in Progress During March. Patt, Inc. purchases and use 8.800 pounds of materials costing $95.640 to make 4,000 tiles Patt's standard material cost per tile is $8 (2 pounds of material $4.001. Compute the total price, and quantity material variances for Patt. Inic for March. Identify whether the variance is favorable or unfavorable! Total Material Variance $ Materials Price Variance 5 Materials Quantity Variance $ Not Aplicable Fw Un Save for Attempts of used