Question: Current Attempt in Progress Fill in the partially completed inventory record shown here. Put the answers down into the table (If answer is zero, please

Current Attempt in Progress Fill in the partially

Current Attempt in Progress Fill in the partially completed inventory record shown here. Put the answers down into the table (If answer is zero, please enter 0, do not leave any fields blank): Item: AB500 Parent: None Lot Size Rule: L4L Children: AB501, AB511, AB521 Lead Time: 2 week Week 1 2 3 4 Gross Requirements 0 0 125 250 Scheduled Receipts Proje Available o Planned Orders e Textbook and Media Save for Later Attempts: 0 of 3 used Submit