Question: Current Attempt in Progress If you accept the potential risk, continue operating with no controls, and absorb any damages that occur, you have adopted a
Current Attempt in Progress
If you accept the potential risk, continue operating with no controls, and absorb any damages that occur, you have adopted a risk
strategy.
avoidance
limitation
acceptance
transference