Current Attempt in Progress
In 2024, Sandhill Corp. started a construction job with a total contract price of $19000000. The job was completed on December 15,2025. Additional data are as follows:
\table[[,2024,2025],[Actual costs incurred during the year,$7500000,$8550000],[Estimated remaining costs,7500000,-],[Billed to customer,6600000,13000000],[Received from customer,5400000,13600000]]
Under the cost-recovery method, what amount of gross profit should Sandhill recognize for 2025?
$1475000
$983333
$2050000
$2950000